Site Clearing
Site clearing for phase 2 begins, which involves removing trees and small shrubs.
Site clearing for phase 2 begins, which involves removing trees and small shrubs.
3NE receives regulatory approvals from the Alberta Utilities Commission (AUC) to construct and operate phase 2 of the solar farm.
Phase I is complete 400 kW phase I solar project is operational and producing power with enough power for 75
The 600 kW Phase I solar project is operational and producing enough power for 75 homes.
The environmental assessment is a key step to ensure there is minimal impact to the environment and community.
Community holds an event to celebrate the launch of the joint project. Official signing between Athabasca Chipewyan First Nation (ACFN),
Incorporation of Three Nations Energy GP Inc and establishment of Three Nations Energy Limited Partnership.